A standard kitchen renovation takes 6-10 weeks from start to finish: Week 1-2 for demolition and structural work, Week 3-4 for rough plumbing/electrical and insulation, Week 5-6 for drywall and flooring installation, Week 7-8 for cabinet and countertop installation, and Week 9-10 for backsplash, finishing, and final inspections. Timeline varies based on project complexity, with simple cabinet refacing taking 2-3 weeks while major structural modifications may extend to 12+ weeks. Our project management ensures efficient scheduling and coordination.